1 Control Power Verification Procedure

1.1 Pre-Measurement PrepAration

  1. Power Down:

    • Turn OFF CP circuit breaker

    • Connect all plugs on:
      • Main PCBs (P1, R1, B1, E1, E2, Z1)
      • DC-DC power units
      • Optional function modules (if equipped)

  2. Power Up Sequence:

    • Close switches/breakers listed in Table 1

    • Turn ON CP breaker

    • Measure voltages at designated test points


2. Control Power Standards

2.2 DC Power Circuits

Circuit Breaker Test Point Standard Tolerance Signal Name
Brake System CR1 T2-15 ~ T2-13 DC125V ±5% 79-1 ~ 00
P1 Board Supply CR2 T2-06 ~ T2-13 DC51V ±5% 420 ~ 400
Safety Loop CR3 T2-17 ~ T2-13 DC125V ±5% 79-2 ~ 00
Car Top Station CST T2-01 ~ T2-13 DC200V ±5% C200 ~ C00
Hall Station HST1 T2-18 ~ T2-13 DC125V ±5% H79 ~ H00
Inverter Main — DCP ~ DCN DC630V 610-630V —
Battery Charge — C1D-P01 ~ C1D-P03 DC52V ±5% BP_PW ~ B00

2.3 Switchboard Power Supply

Output Connector Pin Standard Tolerance
-12V P1 POWIN P01-P04 (-12V~GND) DC-12V ±10%
+12V P1 POWIN P03-P04 (+12V~GND) DC+12V ±10%
+5V P1 POWIN P05-P04 (+5V~GND) DC+5V ±5%

2.4 AC Power Circuits

Circuit Breaker Test Point Standard Tolerance Signal Name
Fans/Lights — T6-01 ~ T6-03 AC220V 220-230V LG1 ~ LG2
Lighting LIH LT-07 ~ LT-08 AC220V 220-230V L10D ~ L20D
  LIGHT LT-03 ~ LT-04 AC220V 220-230V L10 ~ L20
  PL LT-05 ~ LT-06 AC220V 220-230V L10A ~ L20A

3 Critical Measurement Notes

  1. Inverter DC Bus:

    • Must stabilize between 610-630V within 30s of power-up

    • If <600V: Check rectifier module and pre-charge circuit

  2. Battery Circuit:

    • Verify 52V±5% before connecting batteries

    • Low voltage may indicate charger PCB failure

  3. Safety Loop Voltages:

    • 79-1/79-2 to 00: Consistent DC125V ensures relay operation

    • 5% deviation requires immediate investigation


4 Troubleshooting Voltage Anomalies

Symptom Likely Cause Verification Steps
DC51V (CR2) out of range • CR2 breaker contact resistance
• P1 board overload
1. Measure voltage at breaker output
2. Disconnect P1 to isolate
+5V exceeding ±5% • Switchboard regulator failure
• Short circuit on P1
1. Check POWIN pins for debris
2. Measure current draw
AC lighting voltage low • LIGHT breaker thermal damage
• Neutral line corrosion
1. Thermographic scan of breakers
2. Tighten LT terminal blocks

5 Maintenance Recommendations

  1. Quarterly Checks:

    • Clean DC bus capacitor vents

    • Torque test all power terminals (T2/T6/LT series)

  2. Annual Procedures:

    • Replace electrolytic capacitors over 5 years old

    • Calibrate switchboard outputs with reference meter

  3. Safety Notice:

    ‼️ Always discharge DC bus capacitors to <30V before servicing (measure DCP-DCN)

Shanghai Mitsubishi Elevator LEHY Series Control Cabinet Voltage Reference Guide

Working on a similar project?

Send a part number or photo. Our team can help with the next step.

Ask our team
Image detail

Share the part number, product photo, elevator model, and quantity. Our team will help confirm compatibility, availability, and shipping.

Contact FELEVATOR

Send your requirements to our elevator parts team.